Team 16 Web Simulator (2)
Automation in your project board does not apply to archived project board cards. For example, if you close an issue in a project board's archive, the archived card does not automatically move to the "Done" column. When you restore a card from the project board archive, the card will return to the column where it was archived.
The coordinator Bichuan Zuo Week2~3 Bichuan Zuo.
Week4~5 Pengcheng Wang.
Week6~7 Bangfu Yan.
Week8~9 Jiansong Feng.
Week10~Week11 Testing& Review or Add new features
Week12 assessment( group&individual ).
Records: 1st. meeting with clients
Gantt Chart:
gantt
dateFormat MM-DD
title WEB SIMULATOR
%% (`excludes` accepts specific dates in YYYY-MM-DD format, days of the week ("sunday") or "weekends", but not the word "weekdays".)
section 2nd week
1st meeting with clients :done, des1, 03-09, 0d
follow-up meeting :done, des2, 03-12, 3d
research background :done, des3, after des2, 5d
choice for tech-stack :done, des4, after des3, 5d
section 3rd week
prepare for meeting :crit, done,b1, 03-14,2d
headless browser :crit, done,b2, after b1, 2d
meeting with the other team :crit, done,b3, 3d
2nd meeting with client :crit, done,b4, 03-16,0d
set a simple demo individually :done, b5,2d
pitch presentation :milestone, 04-01, 0d
section 4th week
Q&A discussion :active, c1,03-22, 0d
3rd meeting :active, c2,03-23, 20h
follow-up meeting :active, c3, after c2 , 48h
add functionality for scroll-up :c4,after c3,7d
prepare for pitch presentation :crit,active,c5,after c3,5d
section 5th week
pitch presentation :d1,03-28, 3d
test :d2,after c4,20h
Add fuction to demo page :d3,after c5, 48h
section 6th week
set prototype: :e1,03-28, 3d
click&scroll with sub-act :e2,after c4,20h
link to object: :e3, 48h
milestone1 :milestone, after e3, 0d
section 7th week
click&scroll&key :f1, after e3, 3d
test :f2, after f1,2d
Add to demo page :f3, after f2,48h
section 8th week
Update any issue or bug :g1, after f3, 3d
test with the other team: :g2, after g1, 20h
report to clients :g3, after g2, 48h
section 9th week
add function to find object by cooridnate :h1, after g3, 5d
test :h2, after h1,20h
test for return to the scrap team :h3, after h2, 12h
section 10th week
Finalise the project :i1, after h3, 7d
documention :i2, after i1, 7d
1st demo :i3, after i2, 48h
section 11-12th week
perfect UI&UX : j1, after i3, 7d
add extra function to improve: j2, after j1,5d
final presention : j3, after j2, 3d
final report : j4,after j2,3d